Awarded Projects

Awarded Public Works Projects

The Board is required to post certain information related to all public works projects awarded by Nevada government agencies. This requirement is detailed in Nevada Revised Statute 338, resulting from the 2011 Nevada Legislative Session, Senate Bill 268.

If you are authorized by a government agency and would like to post an awarded project, click the button below to complete our online form.

Date

04/15/2021

Company

Odyssey Engineering

Agency Name

Washoe County School District

Project

Poulakidas

Preference

no
Provide Complete design for relocation of portable classroom #6397 from DDES to Poulakidas ES and for relocation of Portable classroom from site TBD to Poulakidas ES

Date

04/15/2021

Company

Farr West Engineering

Agency Name

Truckee Meadows Water Authority

Project

Humboldt-Lander south Main Replacement

Preference

no
Engineering design and construction services for Humboldt Lander south main replacement project.

Date

04/14/2021

Company

Atkins North America, Inc.

Agency Name

Clark County

Project

Silverado Ranch Detention Basin and Roadway Improvements

Preference

no
The construction of a 294 acre-ft detention basin with two inflow storm drains, and an outfall storm storm drain that transitions to a concrete lined open channel. Constructing and widening of Silverado Ranch Boulevard from Arville Street to Dean Martin Drive. Improvements include milling, asphalt and UTACS, striping, signing, storm drain, streetlights, sidewalk, medians, and related appurtenances.

Date

04/06/2021

Company

Poggemeyer Design Group, Inc.

Agency Name

Clark County

Project

NDHILL ROAD – SUNSET ROAD TO DESERT INN ROAD, SPENCER STREET – RUSSELL ROAD TO TWAIN AVENUE AND CAREY AVENUE – PECOS ROAD TO NELLIS BOULEVARD

Preference

no
Roadway improvements for three (3) separate roadway construction contracts, Sandhill Road from Sunset Road to Desert Inn Road, Spencer Street from Russell Road to Twain Avenue and Carey Avenue from Pecos Road to Nellis Boulevard. Such improvements are to include, at a minimum, hot mix asphaltic concrete pavement providing two (2) to six (6) travel lanes, a two-way left-turn lane with raised medians, storm drainage facilities, curbs, gutters, sidewalks, streetlighting, traffic signals, utility modifications and relocations, traffic control devices, pavement markings, intersecting streets, horizontal and vertical transitions, and other necessary appurtenances required to make a good, complete, and serviceable Project within a 80 to 100 foot right-of-way, except where additional lanes may be required.

Date

04/05/2021

Company

HDR Engineering Inc

Agency Name

Truckee Meadows Water Authority

Project

Water Tank Rehab

Preference

no
Water tank rehab design assistance

Date

04/5/2021

Company

Petty and Associates

Agency Name

Washoe County School District

Project

Reed HS

Preference

no
Professional services for design to replace HVAC roof top unit A13. Design will include complete mechanical, architectural electrical, controls, specifications and construction administration

Date

03/31/2021

Company

Farr West Engineering

Agency Name

City of Reno

Project

2021 Reno Consolidated Sewer Rehabilitation Phase I

Preference

no
In general, this project consists of sewer interceptor relocation in the downtown area on Fourth Street between Virginia Street and Center Street. This project also includes upsizing an existing sewer interceptor on Oddie Boulevard east of Silverada Boulevard. It further includes upsizing a sewer main through and near the intersection of Lemmon Drive and Sky Vista Drive.

Date

03/30/2021

Company

CMWorks, Inc.

Agency Name

Clark County

Project

Silverado Ranch Blvd. – Jones Blvd. to Arville St. (Phase B)

Preference

no
Construct a 294 acre detention basin with two inflow storm drains, both consisting of large reinforced concrete boxes and a concrete reinforce box outfall storm drain that transitions to a concrete lined open channel and widening of Silverado Ranch Blvd. from Arville St. to Dean Marting Dr., including milling, hot mix, UTACS, laterals, SW, SLs, ITS conduits, SW medians.

Date

03/30/2021

Company

CMWorks, Inc.

Agency Name

Clark County

Project

Silverado Ranch Blvd. – Jones Blvd. to Arville St. (Phase A)

Preference

no
Silverado Ranch widening from Jones Blvd. to Arville St. (Phase A) and Decatur Blvd. From Gary Ave. to approx. 700-ft south of Silverado Ranch Blvd. to accommodate two 11′ lanes, each direction, 12′ raised median, 4′ to 8′ paved shoulders, ITS conduit, storm drainage. Including milling, hot mix, UTACS, CCRFD facilities, including Decatur Blvd. drain, drop inlets, manholes, storm drain pipes.

Date

03/30/2021

Company

Jacobs Engineering

Agency Name

Truckee Meadows Water Authority

Project

Spring Creek Well 6 & 7 pH Adjustment

Preference

no
Engineering services for Spring Creek Well 6 & 7 pH adjustment.

Date

03/27/2021

Company

Ashley & Vance Engineering Inc.

Agency Name

Carson City

Project

MAC Parking Lot Civil Engineering Services

Preference

no
Ashley & Vance was selected to provide civil engineering services for the Robert “Bob” Crowell Multi-Purpose Athletic Center (MAC) west parking lot.

Date

03/27/2021

Company

Lumos & Associates, Inc.

Agency Name

Carson City

Project

Ross Gold Park ADA Restroom Renovation – Materials Testing

Preference

no
Lumos has been selected to provide materials testing services for the Ross Gold Park ADA Restroom Renovation Project.

Date

03/27/2021

Company

Rifle Range Structural Engineering Services

Agency Name

Carson City

Project

Rifle Range Structural Engineering Services

Preference

no
Lumos has been selected to provide professional structural engineering services associated with the design of the new baffles and eyebrows at the existing range facility.

Date

03/25/2021

Company

Lumos & Associates

Agency Name

City of Reno

Project

2021 Reno Preventative Maintenance Project

Preference

no
Construction Management, Material Testing, and Inspection Services

Date

03/24/2021

Company

RO Anderson Engineering, Inc.

Agency Name

Carson City

Project

Surveying Services for Corparte Yard Parking Lot

Preference

no
RO Anderson has been selected to provide surveying services in order for Carson City Public Works to complete the design of the corporate yard parking lot project.

Date

03/24/2021

Company

Lumos and Associates Inc.

Agency Name

Carson City

Project

Colorado Street Topographic and Right of Way Services

Preference

no
The project scope includes, topographic field survey and right-of-way investigation along Colorado Street between S. Carson Street and Saliman Road.

Date

03/24/2021

Company

Nichols Consulting Engineers

Agency Name

Carson City

Project

Nichols Lane Drainage Improvement Design

Preference

no
NCE has been selected to provide design of drainage improvements for the intersection of Sneddon Way and Carmine St. to connect to a new stown drain alignment on Nichols Lane.